• Approved by Congress in 1974.

• Finished in 1992.

• Then ran for nine months until flood damage shut it down.

• Left idle for years after it was repaired because the Colorado River had plenty of water for a long time.

• Had a 90-day trial run in 2007 at 10 percent of capacity.

• A yearlong trial starts Monday.