As work winds down on Orange Grove Road, all travel lanes are scheduled to open next week, according to Sandi Garrick of the Pima County Project Management Office. 

However, some work such as landscaping will continue.

Permanent striping is scheduled for Aug. 19 to Aug. 20.

The construction project widened the road to two lanes in each direction and added a center turn lane from North Camino de la Tierra to North La Cholla Boulevard.

Garrick said the project is on budget and on schedule, thanks to general contractor Southern Arizona Paving & Construction Co. and engineering firm DOWL HKM.